Suasana iDamanJR
the construction of our dream house at nusa Idaman Nusajaya

76. stairways to syurgawijr

8:26 AM

css carpet furnishing
johor jaya
Posted by ShoZu
Read On 0 comments

75. Delivery

3:12 AM
Saturday, 27/03/10
A day full of deliveries.

Reached idaman about 3.30 pm met with 4X family (many many thanks to them for overseeing) whom was at our home since 10.00 am in the morning for appointment of the carpet guys laying the carpet.  The work was completed soon after we arrived.

Almost immediately after they left all the 3 deliveries that we arranged came one after another.

1. Anda Perabot -
Queensize bedset w/ mattress (guest room)
Canopy bedframe + mattress + wardrobe + dressing table + side table (gals' bed)

2. iBenz
Single bedframe + pullover bed w/ 2mattresses
1 Kingkoil mattress

3. Clover
Masterbed frame (blink blink)
Sofa set
Read On 0 comments

74. Hujan Rahmat

6:54 AM
Sun, 21/03 midday just after JJ finished with installing the sprinklers it rained.
It was really a downpour, raining hard and heavy pouring washing over our house.
Read On 0 comments

73. 5 days of turning our house into a home

6:39 AM
Last week as from Wednesday, 17/03 straight to Sunday, 21/03 we were going in and out crossing the causeway for 5 straight days.  Each day going in as early as dawn and getting back home ard eleventish.

We've set appointments with the various contractors, carpeting, nursery and other errands to coincide with our school holiday leaves.  Earlier we thought that all works could be completed before the school holidays as all the construction works were done but due to some inevitable setbacks (expected I guess) the final carpentering still going on making it impossible for the final acid wash of the whole house to be done in the same week.

The tight schedule we oversee were:
Wed, 17/03: went in just the 2 of us
1. contractors clearing out the rubbish
2. work on transforming the garden
3. went to Ah foo nursery @ Pontian with abg K order of plants

Thurs, 18/03: went in just the 2 of us
1. work on feature wall & family room platform begins
2. css carpet guy came to measure & quote for the stairs & master bedroom
3. work and installation of aluminium wardrobe @ masterbedroom walk-in-wardrobe
4. buying of lightings, paintings and porcelain sinki

Fri, 19/03: went in with the kidz with suffi & haatim overnite at Horizon Hill
1. work on feature wall continues
2. installation of lightings done by JJ
3. painting of verandah interior white and exterior green done by JJ and MKN

Sat, 20/03: went in just the 2 of us with suffi & haatim came in later from 4X
1. work on feature wall continues with them replacing the dented formica and took out the door to be fixed next tuesday to complete with the border for the family platform.
2. electrician men came to fix our TV on the unfinished feature wall, lightings for this area and the platform area plus the garden lightings
4. Aircon guys came and installed all aircons
3. Nursery apek came & planted the 5 plants
4. painting work continues final layers done by JJ and 4X

Since we've our aircons we decided to overnight there.  Our very first stayover the experience was shared with Suffi & Haatim very excited! after clearing the masterbedroom we laid down our inflatable matteresses with the aircon on and had a contented sleep there, syukur about 80% of our dream realised....Amin.

Sun, 21/03: woke up feeling tired otherwise jubilant.
1. JJ doing gardening fixing the sprinklers
2. the washing guys didnt turn up reschedule to next thursday
3. Alex came handover 3rd payment to him
4. we did some final clearing for thurs washing
5. set for sg home early in the evening to avoid the holiday jam

phew setting our home is not an easy task but definitely an exciting journey
Read On 0 comments

72 Feature wall

7:55 AM

18/03/10
Family room platform fixed
Living room feature wall work-in-progress

and yes we felt a lot safer with the grilles installed!
Posted by ShoZu
Read On 0 comments

71. The Garden

5:41 AM
We finally have our garden.
8. A palm tree, 3 sets of bamboo, a small fern & a fushia (batik) 2 layered tree.
7. on saturday, 20/03 the electrician came to fix the lights and to our dissapointment were told that the bali stones not suitable so we had to get these tall lightings which we got for a bargain @ only costing RM$100 and on the same day the nursery apek (from pontian) came with the 5 ordered plants which they helped to plant it straightaway.  In the picture below taken the following day my very own gardener JJ installing the sprinklers.

5. original plan the bali garden lights holder but alas... :(
4. by evening all done

3. laying of pipe for the covered drain

2. the sand for the plot

1. the rubbish being cleared
On wednesday, 15/03 the small precious plot of land had been cleared and the drain was covered.  Carpeted grass were nicely laid down and planted.
Read On 0 comments

70. Supervising

7:48 AM

17/03/10
workers clearing the dumps,
workers inserting pipings in concealed drains
workers preparing for The Garden

Posted by ShoZu

Read On 0 comments

69. bright lights in a rainy day

8:04 AM

13/03-14/03/10
this weekend we see the lights. All the downlights has been installed. ilike.
and it the rains was a nice welcome after eduring hot spells past weekends.
Luv the smell of rain, the sound of it hitting the roof and the gush of winds swaying the trees and engulfing us @ the open verandah.
iluv.

Posted by ShoZu

Read On 0 comments

68. outdoor painting

7:51 AM

Big boy Small man.

Posted by ShoZu

Read On 0 comments

67. my Island space

7:44 AM

the painting continues into the 3rd week. the look to achieve here will be pure white spacious inspiring where i'll be spending my time cooking with luv for my loved ones esp these two hardworking guys hard@work - many many thanks to my darlings for taking the orders patiently from the very cerewet chief chef ;)

Posted by ShoZu

Read On 0 comments

66. my Dream Kitchen

4:21 AM

The plan of the wet and dry kitchen + the false ceiling at the dry area.
going for Green

Posted by ShoZu

Read On 0 comments

65. Painted walls

4:08 AM

contrasting dark grey stairs set against the sunrays

Posted by ShoZu

Read On 0 comments

64. Painted masterRoom

4:04 AM

Royal purple

Posted by ShoZu

Read On 0 comments

Work-In-Progress

Lets talk


ShoutMix chat widget

Dayoh


purchase & ink on 29/03/09

Nusajaya Development Sdn Bhd
No 7 Jln Persiaran Idaman
Nusa Idaman 79100 Nusajaya

Mac 2010 completion S IdamanJR in

as at 21/03/2010 a new lifestyle


visitor